Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Gulf Production manufactures recycle bins using recycled plastic that it sells t

ID: 2474192 • Letter: G

Question

Gulf Production manufactures recycle bins using recycled plastic that it sells to municipal governments. It has developed the following per unit standard costs for 2014 for each bine:

Direct Materials Direct Labor Manufacturing Overhead
Standard quantity 3 pounds ½ hour ½ hour
Standard price $0.80 $12.00 $4.50
Unit standard cost $2.40 $6.00 $2.25

In 2014, the company planned to produce 40,000 bins at a level of 20,000 hours of direct labor. Actual results for 2014 are presented below:

1. Direct materials purchased and used were 116,000 pounds of plastic that cost $98,600.
2. Direct labor costs were $258,300 for 21,000 direct labor hours actually worked.
3. Total manufacturing overhead was $88,000.
4. Actual production was 40,200 bins.

Instructions
Compute the following variances: (Be sure to indicate if it is favorable or unfavorable)

1. Direct materials price
2. Direct materials quantity
3. Direct labor price
4. Direct labor quantity

Explanation / Answer

Answer for question no.1:

Formula for Direct material price variance =Actual quanity*(Standard price- Actual price)

Given actual quantity =116,000 pounds.

Actual price=$98.600/116000

=0.85

Standard Price =$0.80

Substituting the values in the formula=116,000*($0.80-$0.85)

=116,000*-0.05

=$5,800(U).

Answer for question no.2:

Formula for direct materials usagae variance = Standard price*(Standard quantity-Actual quantity)

Given standard price =0.80 perr pound

Actual quantity =116,000 pounds.

Actual production =40,200 units

Standard quantity required for producing 40,200 units=40,200*3 pounds

=120600 pounds.

Substituting the values in the formula =0.80(120600-116,000)

=0.80*4,600

=$3,680(F).

Answer for question no.3:

Formula for direct labour price variance= Actual hours*(Standard price-Actual price)

Given actual hours =21,000 hours.

Standard price= $12 per hour.

Actual price=$258300.

Substituting the values in the formula =21000*12-$258,300

=$252,000-$258,300.

=6,300(U).

Answer for question no.4:

Formula for direct labour quantity variance=Standard price per hour*(standard hours for actual quantity - Actual quantity)

Given standard price=$12.

Standard hours for acutal quantity=40,200*0.50

=20,100 hours.

Substituting the values in the formula = $12*(20,100 - 21,000)

=$12*-900

=10,800(U).