Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Dante\'s Statue Company produces lawn statues. The standard cost of producing on

ID: 2472542 • Letter: D

Question

Dante's Statue Company produces lawn statues. The standard cost of producing one statue is:

Material (2.5 pounds × $2.80) $ 7.00

Labor (.75 hours × $12) 9.00

Overhead 10.00

Total $26.00

-----------------------------------------------------------------------------------------------------------

Standard variable overhead is $6.20 per unit, and fixed annual overhead is $95,000. At the start of 2012, expected production was 25,000 units. During 2012, 27,000 statues were produced. The following information, related to actual costs incurred in 2012, is available:

1.  Purchased 70,000 pounds of material for $182,000.

2.  Used 68,200 pounds of material.

3.  Worked 19,600 labor hours costing $254,800.

4.  Actual overhead incurred was $260,000.

Required:

a.  Show the calculation of the standard overhead rate per unit of $10.

b.  Calculate all material, labor, and overhead variances.

c.  Prepare a variance summary, and briefly comment on variances that should be investigated.

Explanation / Answer

Variable overhead

$6.20

Fixed overhead 95,000/25,000

   3.80

total

$10.00

b) Material price variance = ( 2.80 *70,000 – 182,000)

                                                =14,000(F)

Material Quantity variance = ( 2.5*27,000 - 68,200) 2.80

                                                 = 1,960 (U)

Direct labor price variance = ( 12* 19,600 - 254,800)

                                                  =19,600(U)

Direct labor efficiency variance = (.75*27,000 – 19,600) 12

                                                          = (20,250 – 19,600) 12

                                                          = 7,800 (F)

Controllable overhead variance = Actual overhead – flexible budget for actual production

                                                               = 260,000 – (27,000 *6.20 + 95,000)

                                                              =2,400 (F)

Overhead volume variance = Flexible budget for actual production – overhead applied

                                                  = 262,400 – (10 *27,000)

                                                  = 7,600 (U)

3)The material price variance is favorable since the actual cost is less than estimated but the quantity variance is unfavorable since more units are consumed than anticipated . similarly the actual price of labor is more but there is efficiency in working hence less hours consumed.

The controllable overhead is favorable , also this variance is controllable .

Variable overhead

$6.20

Fixed overhead 95,000/25,000

   3.80

total

$10.00