Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Produc
ID: 2472285 • Letter: S
Question
Stage 2 ABC for Manufacturing:
Reassigning Costs to Cost Objectives Regal Products has developed the following activity cost information for its manufacturing activities: Activity Activity cost Machine setup $80.00 per batch
Movement 15.00 per batch move 0.10 per pound
Drilling 3.00 per hole
Welding 4.00 per inch
Shaping 25.00 per hour
Assembly 19.00 per hour I
nspection 2.00 per unit
Filling an order for a batch of 50 fireplace inserts (each insert weighing 150 pounds) required the following: Three batch moves
Two sets of inspections
Drilling five holes in each unit
Completing 80 inches of welds on each unit
Thirty minutes of shaping for each unit
One hour of assembly per unit
Determine the activity cost of converting the raw materials into 50 fireplace inserts.
Explanation / Answer
Activity Cost Cost Calculation Setup $80.00 per batch 240.00 80*3 Movement 15.00 per batch move 0.10 per pound 45.00 750.00 (15.00*3) and .10*50*150 pounds Drilling 3.00 per hole 750.00 5*50*3 Welding 4.00 per inch 16,000.00 80*50*4 Shaping 25.00 per hour 625.00 1/2*50*25 Assembly 19.00 per hour I 950.00 1*19*50 Inspection 2.00 per unit 100.00 50*2 285.00 19,175.00 19,460.00
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.