Dawson Toys, Ltd., produces a toy called the Maze. The company has recently esta
ID: 2471681 • Letter: D
Question
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0 31 per micron Direct labor 1.1 hours per toy at $6.60 per hour During July, the company produced 4,700 Maze toys. Production data for the month on the toy follow: Direct materials: 70,000 microns wore purchased at a cost of $0.29 per micron. 23,000 of these microns were still in inventory at the end of the month. Direct labor 5,770 direct labor-hours were worked at a cost of $39,813. Compute the following variances for July: (Do not round intermediate calculations. Round final answer to the nearest whole dollar. Indicate the effect of each variance by selecting "F" for favorable, "IT for unfavorable, and "None" for no effect (i.e., zero variance).) The materials price and quantity variancesExplanation / Answer
DM Quantity Variance => Stnd 8 mics x 4700 = 37600 vs Actual 47000 = 9400 x .31 => 2914 U
DM Price Variance => 0.02 x 70000 => 1400 F
DL Rate Variance => Stnd 6.60 vs Actual 6.90 => 0.30 x 5770 => 1731 U
DL Efficiency Var => Stnd 1.1 x 4700 = 5170 vs Actual 5770 => 600 x 6.60 => 3960 U
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.