Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Lift Jack Company has seven activity cost pools and two products. It expects to

ID: 2471664 • Letter: L

Question

Lift Jack Company has seven activity cost pools and two products. It expects to Products 200.000 units of its automobile scissors, jack and 80.000 units of truck hydraulic jack. Having identified its activity cost pools and the cost drivers for each cost Pool. Lift jack company accumulated the following data relative to those activity cost pools and cost drivers. Traditionally the manufactural overhead cost has been applied to work in process based on Direct Labor hours. Under the traditional method what is the overhead rate per direct labor hour and how much overhead is applied to each scissors jack and hydraulic jack. Prepare a schedule showing the computations of the activity-based overhead rates per cost driver under ABC Prepare a schedule assigning each activity's overhead cost to the two products using ABC. Compute the overhead cost per unit for each product using ABC ? Comment on the comparative overhead cost per unit.

Explanation / Answer

1

Calculation of overhead allocation using traditional method:

Total manufacturing overhead (A)

$                6,800,000

Total Direct labor hours (B)

200,000

Hours

Overhead allocation rate = A/B =

$                      34.00

Per Direct Labor Hour

Allocation of Overhead to products:

Scissors Jacks

Hydraulic Jacks

Total Direct labor hours (A)

130000

70000

Overhead allocation rate (B)

$                      34.00

$              34.00

Allocation of Overhead = A*B =

$                4,420,000

$        2,380,000

2

Calculation of Activity Based Overhead Rates:

Activity Cost Pools

Estimated Overhead

Total Activity

Overhead Rate

A

B

A/B

Ordering and Receiving

$                  200,000

2,500

$                    80.00

Machine Setup

$                  600,000

1,200

$                  500.00

Machining

$                2,000,000

800,000

$                     2.50

Assembling

$                1,800,000

3,000,000

$                     0.60

Inspecting and testing

$                  700,000

35,000

$                    20.00

Painting

$                  300,000

3,000,000

$                     0.10

Supervising

$                1,200,000

200,000

$                     6.00

3

Assignment of Overhead cost to products using ABC :

For Scissors Jacks :

Activity Cost Pools

Total Activity

Overhead Rate

Assigned Overhead

A

B

A*B

Ordering and Receiving

1,000

$              80.00

$             80,000.00

Machine Setup

500

$             500.00

$            250,000.00

Machining

300,000

$                2.50

$            750,000.00

Assembling

1,800,000

$                0.60

$         1,080,000.00

Inspecting and testing

20,000

$              20.00

$            400,000.00

Painting

1,800,000

$                0.10

$            180,000.00

Supervising

130,000

$                6.00

$            780,000.00

Total Overhead Assigned

$         3,520,000.00

For Hydraulic Jacks :

Activity Cost Pools

Total Activity

Overhead Rate

Assigned Overhead

A

B

A*B

Ordering and Receiving

1,500

$              80.00

$            120,000.00

Machine Setup

700

$             500.00

$            350,000.00

Machining

500,000

$                2.50

$         1,250,000.00

Assembling

1,200,000

$                0.60

$            720,000.00

Inspecting and testing

15,000

$              20.00

$            300,000.00

Painting

1,200,000

$               0.10

$            120,000.00

Supervising

70,000

$                6.00

$            420,000.00

Total Overhead Assigned

$         3,280,000.00

4

Calculation of Overhead cost per unit:

Scissors Jacks

Hydraulic Jacks

Assigned overhead Costs (A)

$           3,520,000.00

$    3,280,000.00

Number of Units (B)

200000

80000

Overhead cost per unit =A/B =

$                      17.60

$             41.00

1

Calculation of overhead allocation using traditional method:

Total manufacturing overhead (A)

$                6,800,000

Total Direct labor hours (B)

200,000

Hours

Overhead allocation rate = A/B =

$                      34.00

Per Direct Labor Hour

Allocation of Overhead to products:

Scissors Jacks

Hydraulic Jacks

Total Direct labor hours (A)

130000

70000

Overhead allocation rate (B)

$                      34.00

$              34.00

Allocation of Overhead = A*B =

$                4,420,000

$        2,380,000

2

Calculation of Activity Based Overhead Rates:

Activity Cost Pools

Estimated Overhead

Total Activity

Overhead Rate

A

B

A/B

Ordering and Receiving

$                  200,000

2,500

$                    80.00

Machine Setup

$                  600,000

1,200

$                  500.00

Machining

$                2,000,000

800,000

$                     2.50

Assembling

$                1,800,000

3,000,000

$                     0.60

Inspecting and testing

$                  700,000

35,000

$                    20.00

Painting

$                  300,000

3,000,000

$                     0.10

Supervising

$                1,200,000

200,000

$                     6.00

3

Assignment of Overhead cost to products using ABC :

For Scissors Jacks :

Activity Cost Pools

Total Activity

Overhead Rate

Assigned Overhead

A

B

A*B

Ordering and Receiving

1,000

$              80.00

$             80,000.00

Machine Setup

500

$             500.00

$            250,000.00

Machining

300,000

$                2.50

$            750,000.00

Assembling

1,800,000

$                0.60

$         1,080,000.00

Inspecting and testing

20,000

$              20.00

$            400,000.00

Painting

1,800,000

$                0.10

$            180,000.00

Supervising

130,000

$                6.00

$            780,000.00

Total Overhead Assigned

$         3,520,000.00

For Hydraulic Jacks :

Activity Cost Pools

Total Activity

Overhead Rate

Assigned Overhead

A

B

A*B

Ordering and Receiving

1,500

$              80.00

$            120,000.00

Machine Setup

700

$             500.00

$            350,000.00

Machining

500,000

$                2.50

$         1,250,000.00

Assembling

1,200,000

$                0.60

$            720,000.00

Inspecting and testing

15,000

$              20.00

$            300,000.00

Painting

1,200,000

$               0.10

$            120,000.00

Supervising

70,000

$                6.00

$            420,000.00

Total Overhead Assigned

$         3,280,000.00

4

Calculation of Overhead cost per unit:

Scissors Jacks

Hydraulic Jacks

Assigned overhead Costs (A)

$           3,520,000.00

$    3,280,000.00

Number of Units (B)

200000

80000

Overhead cost per unit =A/B =

$                      17.60

$             41.00

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote