The following time-phasing chart is available for a single item within a MRP sys
ID: 2466797 • Letter: T
Question
The following time-phasing chart is available for a single item within a MRP system. Complete this chart by estimating inventory on hand and planned order release values. Lead time is 2 weeks and order policy is 100 units, which means this part can be ordered only in 100-unit batches. Inventory replenishment is JIT, lead times are negligible.
Week Number
1
2
3
4
5
6
7
8
9
10
Gross Requirements
80
95
110
50
Schedule Receipt
100
Inventory on Hand
Planned order Release
Week Number
1
2
3
4
5
6
7
8
9
10
Gross Requirements
80
95
110
50
Schedule Receipt
100
Inventory on Hand
Planned order Release
Explanation / Answer
Week Number
Week Number
1 2 3 4 5 6 7 8 9 10 Gross Requirements 0 0 80 95 0 110 0 0 50 0 Schedule Receipt 100 0 0 100 0 100 0 0 100 0 Inventory on Hand 100 100 20 25 25 15 15 15 65 65 Planned order Release 0 100 0 100 0 0 100 0 0 0 Lead Time = 2 weeksRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.