Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. Fletcher Company collected the following data regarding production of one of

ID: 2464496 • Letter: 1

Question

1.

Fletcher Company collected the following data regarding production of one of its products. Compute the total direct materials variance.

a. $6,000 favorable.

b. $3,570 unfavorable.

c. $2,430 favorable.

d. $6,000 unfavorable.

e. $3,570 favorable.

3.

Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10 per pound to produce 2,000 units. What is the direct materials price variance?

a. $400 unfavorable.

b. $450 unfavorable.

c. $2,500 unfavorable.

d. $2,550 unfavorable.

e. $2,950 unfavorable.

4.

Grant Co. uses the following standard to produce a single unit of its product: Variable overhead (2 hrs. per unit @ $4/hr.) Actual data for the month show total variable overhead costs of $190,000, and 23,000 units produced. The total variable overhead variance is:

a. $6,000F.

b. $6,000U.

c. $78,000U.

d. $78,000F.

e.$0.

Direct materials standard (6 lbs. @ $2/lb.) $12 per finished unit Actual direct materials used 243,000 lbs. Actual finished units produced 40,000 units Actual cost of direct materials used $483,570

Explanation / Answer

Answer for question no.1:

Total direct material variance = Standard material cost - Actual material cost

=40,000*$12 - $483,570

=$480,000 - $483,570

=$3,570 (U)

Therefore, answer is option B.

Answer for question no.3:

Formula for direct material price varince = Actual material used*(Standard material price - Actual material price)

=4500 *($5 - $5.10)

=4500 * -$.10

=$450(U)

Answer is option B.

Answer for question no.4:

Formula for total variable overhead variance = Standard variable overhead cost - Actual variable overhead

= 23,000*2hrs*$4 per hour - $190,000.

=$184,000 -$190,000

=$6,000(U).

Answer is option b.