Management of Mitol Rhoin AG of Kon, Germany, would like to reduce the amount of
ID: 2463488 • Letter: M
Question
Management of Mitol Rhoin AG of Kon, Germany, would like to reduce the amount of hme between when a cuslomer places an order and when the order is shipped For the first quarter of operations duning the current year the following data were reported 0 3 days nspection time Wait time (from order to start of production) 14.0 days Process time Move time Queue time 7 days 1.0 days 50 days Required: 1. Compute the throughput ime days 2. Compute the manufacturing cycle efficiency (MCE) for the quarter (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value added activitios? 4 Compute the delivery cycle time daysExplanation / Answer
1) Throughput time
2) Manufacturing Cycle Effeciency (MEC)
MCE= Process time / Throughput time
= 2.7 / 9
= 0.30
3) Throughput time in Non Value added activities
Non value added activities = Queue time + Move time + Inspection time
= 5 + 1 + 0.30
= 6.30
= Non value activities / Throughput time
= 6.30 / 9.0
= 70%
4) Delivery Cycle time
= Wait time + Throughput time
= 14 + 9
= 23 Days
5) New through put
= Old throughput - Queue time
= 9 - 5
= 4 days
MCE = Process time / Throughput time
= 2.7 / 4
= 0.675
Particulars Days Process time 2.7 Inspection Time 0.3 Move time 1.0 Queue time 5.0 Total 9.0Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.