Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

?(Long-Term Contract with an Overall Loss) On July 1, 2012, Torvill Construction

ID: 2463353 • Letter: #

Question

?(Long-Term Contract with an Overall Loss) On July 1, 2012, Torvill Construction Company Inc. contracted tobuild an office building for Gumbel Corp. for a total contract price of $1,900,000. On July 1, Torvill estimatedthat it would take between 2 and 3 years to complete the building. On December 31, 2014, the building wasdeemed substantially completed. Following are accumulated contract costs incurred, estimated costs tocomplete the contract, and accumulated billings to Gumbel for 2012, 2013, and 2014

Explanation / Answer

Computation of Recognizable Profit/Loss

Percentage-of-Completion Method

2012

Costs to date (12/31/12)                                                           $ 300,000

Estimated costs to complete                                                1,200,000

Estimated total costs                                                      $1,500,000

Percent complete ($300,000 ÷ $1,500,000)                       20%

Revenue recognized ($1,900,000 X 20%)                          $ 380,000

Costs incurred                                                                           (300,000)

Profit recognized in 2012                                                         $ 80,000

2013

Costs to date (12/31/13)                                                          $1,200,000

Estimated costs to complete                                                800,000

Estimated total costs                                                      2,000,000

Contract price                                                                             (1,900,000)

Total loss                                                                                     $ 100,000

Total loss                                                                                     $ 100,000

Plus gross profit recognized in 2012                                   80,000

Loss recognized in 2013                                                          $ 180,000

2014 revenue

($1,900,000 –$380,000–$760,000)                      $ 760,000

Less: 2014 estimated costs                                       800,000

2014 loss                                                              $ (40,000)

2014

Costs to date (12/31/14)                                                 $2,100,000

Estimated costs to complete                                          2,100,000

Contract price                                                                   1,900,000

Total loss                                                                            $ (200,000)

Total loss                                                                            $ (200,000)

Less: Loss recognized in 2013                                 $180,000

Gross profit recognized in 2012                                (80,000) (100,000)

Loss recognized in 2014                                               $ (100,000)

(b) Computation of Recognizable Profit/Loss

Completed-Contract Method

2012—NONE

2013

Costs to date (12/31/13)                                                 $1,200,000

Estimated costs to complete                                       800,000

Estimated total costs                                                      2,000,000

Contract price                                                                   1,900,000

Loss recognized in 2013                                                 $ (100,000)

2014

Total costs incurred                                                        $2,100,000

Total revenue recognized                                               1,900,000

Total loss on contract                                                     (200,000)

Deduct loss recognized in 2013                                  (100,000)

Loss recognized in 2014                                                 $ (100,000)

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote