The following data is given for the stringer Company: Determine the direct mater
ID: 2460206 • Letter: T
Question
The following data is given for the stringer Company:
Determine the direct material quantity variance.
Select the correct answer.
Budgeted production 1,034 units Actual production 913 units Materials: Standard price per ounce $1.78 Standard pounds per completed unit 10 Actual pounds purchased and used in production 8,856 Actual cost of materials $18,155 Labor: Standard hourly labor rate $14.00 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,701.95 Actual total labor costs $71,705 Overhead: Actual and budgeted fixed overhead $1,068,974 Standard variable overhead rate $27.00 per standard labor hour Actual variable overhead costs $131,655 Overhead is applied on standard labor hours.Explanation / Answer
direct material quantity variance = Std price* (Std qty - Actual quantity) = 1.78*(913*10-8856) = 488 F
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.