Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Use the following to answer questions 29-30: Gomez, Inc. began work in 2010 on c

ID: 2459632 • Letter: U

Question

Use the following to answer questions 29-30:

Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of $7,200,000. Other details follow:

    2010

    2011

Costs incurred during the year

$1,200,000

$3,675,000

Estimated costs to complete, as of December 31

3,600,000

0

Billings during the year

1,350,000

5,400,000

Collections during the year

900,000

5,850,000

      29. Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2010 is

            A) $450,000.    B) $600,000.    C) $1,800,000.    D) $2,400,000.

      30. Assume that Gomez uses the completed-contract method of accounting. The portion of the total gross profit to be recognized as income in 2011 is

                        A) $900,000.    B) $1,350,000.    C) $2,325,000.    D) $7,200,000

    2010

    2011

Costs incurred during the year

$1,200,000

$3,675,000

Estimated costs to complete, as of December 31

3,600,000

0

Billings during the year

1,350,000

5,400,000

Collections during the year

900,000

5,850,000

Explanation / Answer

29) Year 2010 Cost incurred till date 1200000 Estimated costs to complete as of December 31 4800000 ( 1200000 + 3600000) % Complete 25 Total contract value 7200000 Estimated costs to complete 4800000 Gross Profit 2400000 Gross profit in 2010 based on percentage completed method ( 2400000 * 25%) 600000 Hence option B is correct 30) Completed contract method Contract price 7200000 Actual cost incurred 2010 1200000 2011 3675000 4875000 Gross profit 2011 2325000 Hence option C is correct

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote