Activity-based management starts with activity analysis. The four steps in activity analysis are: 1. Chart, from start to finish, the activities used to complete the product or service 2. Classify activities as value-added or non-value-added 3. Eliminate non-value-added activities 4. Continuously improve and reevaluate the efficiency of value-added activities or replace them with more efficient activities. The value-added activities identified in Step 2 make up the a. low cost solution. b. critical path. c. optimal solution. d. value chain.
Explanation / Answer
The value-added activities identified in Step 2 make up the
b. critical path.
At the Stage 2 where activities are classified as value-added or non value-added, segregate the product line in two different activities first Having value-value added and second Having no value-added.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.