At the end of 2014, there was one building project in process , the $45,000,000

ID: 2456851 • Letter: A

Question

At the end of 2014, there was one building project in process , the $45,000,000 SoFancy University project (SFU), which was started in June 2014. The original estimated costs for the SFU project totaled $41,750,000 but there have been substantial increases in the cost of materials resulting in a current total cost estimate of $45,100,000 for the job. The contract does not allow for renegotiation of the contracted price. threeBrothers has a legally binding enforceable contract with both universities and all parties are expected to be able to perform under the contracts. The general ledger account Construction-in-Progress Inventory shows the following before any 2015 year-end adjusting entries.

            

              Construction-in-Progress Inventory                               

                 2014     dr $16,700,000                                     

           2014 aje      dr 900,000                                  

       2015SFU      dr 18,000,000                                                                          

       Unadj       $35,600,000                  

              Billings-on-Contract

2014       cr      $20,000,000         

2015SFU cr      $15,000,000

Unadj.         $35,000,000

I have a general idea how to do this, but having a difficult time getting the correct adjusting entries.

                                                                                                                                                                                               

                                                           

Explanation / Answer

SFU Contract Revenue as per Contract                        45,000,000 Current Cost Estimate                        45,100,000 Expected Loss in Contract                           (100,000) Cost Incurred till2015                        35,600,000 Billing done Till Date                        35,000,000 % Completion = Current cost/Estimated cost= 78.9% % revenue can be recognized                        35,521,064 Under billed amount                                521,064 Adjusting Journal Entries Account Title Dr $ Cr$ Cost in excess of billing                              600,000 Cost of contract (additional loss next year)                                21,064 Sales                       521,064 Loss on Contract                         100,000      As the total loss from contract is known , the total loss of $ 100,000 recognized in 2015 with additional cost recorded as per recommended GAAP. Next year the actual cost will be credited by the same extra   cost recoreded this year.