Question
Multiple Choice Question on Price Variance
Masonry Products Corporation has established the following materials standards for a particular product: Standard quantity per unit of output 6.3 feet Standard price $21.10 per feet The following data relates to operations concerning the product for the last month: Actual materials purchased 1.270 feet Actual cost of materials purchased $26,035 Actual materials used in production 1,170 feet Actual output 270 units What is the materials price variance for the month? $702 F $702 U $762 F $762 UExplanation / Answer
Material price variance = ( Actual price - Standard price ) x Actual quatity used
= ( $20.5 - $21.10 ) x 1170 feet
= $0.6 x 1170 feet
= $ 702 F-favourable since actual price is less than standard price.
Actual price is arrived at as follows
Actual purchase amount = $26035
Actual quantity purchased = 1270 feet
Actual purchase price = Actual purchase amount / Actual quantitiy purchased
= $26035 / 1270 feet
= $20.50