The following data relate to labor cost for production of 4,900 cellular telepho
ID: 2449717 • Letter: T
Question
The following data relate to labor cost for production of 4,900 cellular telephones: Actual: 3,230 hrs. at $14.40 $46,512 Standard: 3,280 hrs. at $14.00 $45,920 a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Rate variance $ Time variance $ Total direct labor cost variance $ b. The employees may have been less experienced or poorly trained, thereby resulting in a labor rate than planned. The lower level of experience or training may have resulted in efficient performance. Thus, the actual time required was than standard.
Explanation / Answer
Direct labor rate variance = (Actual rate - standard rate) * Actual hour
= ($14.40 - $14) * 3230
= $1292
Direct labor time variance = (Actual hrs. * standard rate) - standard cost
= (3230 * 14) - 45920
= 45220-45920
= - $700
total direct labor cost variance= standard hrs * standard rate - actual hrs * actual rate
= (3280 * $14) - (3230 * $14.40)
=$45920 - $46512
= $592
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.