A cost that is traceable to a segment through activity-based costing may or may
ID: 2448141 • Letter: A
Question
A cost that is traceable to a segment through activity-based costing may or may not be an avoidable cost for decision making.
True False
Only future costs that differ between alternatives are relevant in decision making.
True False
Future costs that do not differ between the alternatives in a decision are avoidable costs.
True False
The book value of a machine, as shown on the balance sheet, is not relevant in a decision concerning the replacement of that machine by another machine. (Ignore taxes.)
True False
A cost that is relevant in one decision may not be relevant in another decision.
True False
The book value of old equipment is a relevant cost in a decision to replace that equipment. (Ignore taxes.)
True False
Explanation / Answer
1. True
2. False
3. False
4. False
5. False
6. True