Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Based on the below information, respond to the below questions. Estimated overhe

ID: 2445791 • Letter: B

Question

Based on the below information, respond to the below questions.

Estimated overhead

$320,000

Actual overhead costs incurred

$344,400

Estimated direct labour hours

40,000

Actual direct labour hours worked

42,000

The amount of the overhead variance is:

A) $24,400 overapplied.

B) $24,400 underapplied.

C) $8,400 overapplied.

D) $8,400 underapplied.

The budgeted factory overhead rate for applying manufacturing overhead is:

A) $7.62

B) $8.00

C) $8.20

D) $8.61

If the budgeted factory overhead rate is used to apply overhead, applied manufacturing overhead is:

A) $321,000

B) $328,000

C) $336,000

D) $344,400

Estimated overhead

$320,000

Actual overhead costs incurred

$344,400

Estimated direct labour hours

40,000

Actual direct labour hours worked

42,000

Explanation / Answer

overhead variance = estimate overheads - actual overheads = 320,000 - 344,400 = -24,400. (unfavorable). This is underapplied variance as the budgeted costs are lower than actual costs.

So the answer is option "b" $24,400 underapplied.

Budgeted factory overhead rate = budgeted overhead costs/budgeted labor hours = $320,000/40,000 hours = $8 per hour. The answer is option "b" i.e $8.

budgeted overhead rate = $8. applied overhead = actual hours*budgeted overhead rate

= 42,000 hours*$8 per hour = $336,000. Hence the answer is option "c" i.e $336,000.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote