Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

\"Blast it!\" said David Wilson, president of Teledex Company. \"We\'ve just los

ID: 2445749 • Letter: #

Question

"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $4,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid. Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The Department Fabricating Machining AssemblyTotal Plant $219,000 $109,500 $328,500 $ 657,000 Manufacturing overhead $383,250 $438,000 $ 98,550 $ 919,800 Direct labor Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Department Direct materials Direct labor Manufacturing overhead labricating Machining /exKYnily .10.1 Mart $ 4,900 400 3,300 $ 8,600 $ 6,600 $ 700 8,100 $ 15,400

Explanation / Answer

Answer:

4.

a) Company’s bid price on the Koopers Job if a plantwide overhead rate had been used to apply overhead cost

Company’s bid price = 150% of total manufacturing cost

Total Manufacturing Cost = Direct materials + Direct labor + manufacturing overhead = $8,600 + $15,400 + $21,560 = $45,560

Company’s bid price = 150% x $45,560 = $68,340

b) Company’s bid price if departmental overhead rates had been used to apply overhead cost

Manufacturing Overhead Cost if departmental overhead rates had been applied = $16,780

Total Manufacturing Cost = Direct materials + Direct labor + manufacturing overhead

Total Manufacturing Cost = $8,600 + $15,400 + $16,780 = $40,780

Company’s bid price = 150% of total manufacturing cost = $40,780 x 150% = $61,170

5.

We can analyze Under/Over applied Overhead Costs by comparing Budgeted Cost and Actual Cost.

Under-Applied Overhead Cost arises when Budgeted Overhead Costs are greater than Actual Overhead Costs

Over-applied Overhead Cost arises when Budgeted Overhead Costs are lower than Actual Overhead Costs

a) Computation of underapplied or overapplied overhead for the year (assuming that planwide overhead rate is used)

Total Budgeted Manufacturing Overheads = $919,800

Total Actual Manufacturing Overheads = $964,800

Over-Applied Manufacturing Overheads = Budgeted Overhead – Actual Overhead = $919,800 - $964,800 = $45,000

b) Computation of underapplied or overapplied overhead for the year (assuming that departmental overhead rate is used)

Fabricating

Over-applied Overhead Cost

$11,750

Machining

Over-applied Overhead Cost

$45,000

Assembly

Under-applied Overhead Cost

($11,750)

Total Plant

Over-applied Overhead Cost

$45,000

Working:

Calculation of Budgeted and Actual Overhead Costs

Budgeted Overhead Cost

Actual Overhead Cost

Difference (Budgeted – Actual)

Situation (Under/Over Applied)

Fabricating

$219,000 x 175% = $383,250

$395,000

$11,750

Over-Applied

Machining

$109,500 x 400% = $438,000

$483,000

$45,000

Over-Applied

Assembly

$328,500 x 30% = $98,550

$86,800

$11,750

Under-Applied

Total Plant

$919,800

$964,800

$45,000

Over-Applied

Fabricating

Over-applied Overhead Cost

$11,750

Machining

Over-applied Overhead Cost

$45,000

Assembly

Under-applied Overhead Cost

($11,750)

Total Plant

Over-applied Overhead Cost

$45,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote