Heirloom Company manufactures hand-made pine storage boxes for a variety of clie
ID: 2442763 • Letter: H
Question
Heirloom Company manufactures hand-made pine storage boxes for a variety of clients. As production manager, you have developed the following value chart:Operation Average number of days
Receiving materials 1
Storing materials 2
Handling materials 3
Cutting/measuring materials 6
Assembling materials 4
Building boxes 7
Attaching hinges 2
Inspection 1
a) Determine the value-added activities and their total time
b) Determine the non-value-added activities and their total time
c) Calculate the manufacturing efficiency. (MCE)
Explanation / Answer
a.Value added activities and their total time 1.Cutting /measuring materials =6 2. Assembling materials =4 3. Building boxes =7 4. Attaching hinges =2 5.inspection =1 Total time =20 b.Non value added activities Receiving materials =1 Storing materials =2 Handling materials =3 Total 6 total manufacturing time=20+6=26 c.Manufacturing efficiency= Total manufacturing time/Value added time Manufacturing efficiency=26/20*100=130%Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.