Problem 23-2A (Part Level Submission) Costs and Production Data Actual Standard
ID: 2438762 • Letter: P
Question
Problem 23-2A (Part Level Submission)
Costs and Production Data
Actual
Standard
(a)
Problem 23-2A (Part Level Submission)
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017.Costs and Production Data
Actual
Standard
Raw materials unit cost $2.40 $2.30 Raw materials units used 11,000 10,600 Direct labor payroll $170,200 $167,200 Direct labor hours worked 14,800 15,200 Manufacturing overhead incurred $230,372 Manufacturing overhead applied $233,472 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $69,600 Variable overhead rate per machine hour $3.20 Fixed overhead rate per machine hour $1.60Overhead is applied on the basis of standard machine hours. 3.20 hours of machine time are required for each direct labor hour. The jobs were sold for $471,000. Selling and administrative expenses were $45,000. Assume that the amount of raw materials purchased equaled the amount used.
Explanation / Answer
(I) Material variance
Material Price variance = Actual quantity purchased x (Standard price - Actual price)
= 11,000 x ($2.30 - $2.40)
= $1,100 (Unfavorable)
Material quantity variance = Standard price per unit x (Standard quanitity - Actual quantity used)
= $2.30 x (11,000 - 10,600)
= $920 (Favorable)
Total material variance = Material price variance + Material quantity variance
= $1,100 (U) + $920 (F)
= $180 (Unfavrable)
Labor variance:
Standard labor rate per hour = $167,200 ÷ $15,200 hours = $11
Actual labor rate per hour = $170,200 ÷ 14,800 hours = $11.5
Labor price variance = Actual time x (Standard rate - Actual rate)
= 14,800 x ($11 - $11.5)
= $7,400 (Unfavorable)
Labor quantity variance = Standard rate x (Standard hours for actual output - Actual hours)
Standard hours for actual output = (15,200 ÷ 10,600) x 11,000
= 15,774 hours
Therfore, Labor quantity variance = $11 x (15,774 hours - 14,800 hours)
= $10,714 (Favorable)
Total labor variance = Labor price variance + Labor quanity variance
= $7,400 (Unfavorable) + $10,714 (Favorable)
= $3,314 (Favorable)
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.