Bonus Problem (Extra credit, 5 pts) This is a Fundamentals of Engineering (FE) e
ID: 2436884 • Letter: B
Question
Bonus Problem (Extra credit, 5 pts) This is a Fundamentals of Engineering (FE) exam style problem. The following new pipeline is planned to be installed. The annual maintenance and pumping costs are considered to be paid in their entireties at the end of the years in which their costs are incurred. The pipe has the following costs and properties. The market interest rate is 8%. AMOUNT $3350 $750 50 years ITEM INITIAL COST ANNUAL MAINTENANCE COSTS SERVICE LIFE SALVAGE VALUE $125 $10.75 3000 hours/year PUMP COST/HOUR PUMP OPERATION What is the annual equivalent cost of the pipe?Explanation / Answer
Annual equivalent cost = NPV / total of annuity factor (PVAF)
pvf = 1/(1+r)^n
pvaf = 1-(1+r)-n / n
annual equivalent cost = 407036/12.233
=33273 .6
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.