Haft Construction Company has consistently applied the percentageof completion m
ID: 2433396 • Letter: H
Question
Haft Construction Company has consistently applied the percentageof completion method. On Jan 10, 2008 Haft began work on a$3,000,000 construction contract. At the inception date, theestimated cost of construction was $2,250,000. The following inforelate to the progress of the contact:Income recognized at 12/31/08 300,000 Cost incurred1/10/08 through 12/31/09 1,800,000 Estimated costto compelte at 12/31/09 600,000
1. In its income statement for the year ended Dec 31 ,2009, whatamount of gross profit should Haft report?
Income recognized at 12/31/08 300,000 Cost incurred1/10/08 through 12/31/09 1,800,000 Estimated costto compelte at 12/31/09 600,000
Explanation / Answer
cost incurredso far Recognizedprofit = ---------------------------- x estimatedprofit - previous years'profit totalexpected project costGross profit for 2008 = $300,000 so cost for 2008 = $2,250,000 /$3,000,000 = 75 % of Sales and GP = 25% of sales so cost = $300,000 x 75 / 25 = $900,000 $1,800,000 Recognizedprofit for2009 = ------------------------- x (3,000,000 - 2,400,000) -$300,000 $1,800,000+ $600,000 $1,800,000 = ------------- x $300,000 = $225,000 $2,400,000
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.