Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufactu
ID: 2432402 • Letter: L
Question
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed dircuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of S0 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator moves the assembled boards to the final assembly area. This move takes 10 minutes to complete. The final assembly for each stereo unit requires 22 minutes and is also done in batches of S0 units. A batch of S stereos is moved into the test building, which is across the street. The move takes 20 minutes. Before conducting the test, the test equipment must be set up for the particular stereo model. The test setup requires 30 minutes. The units wait while the setup is performed. In the final test, the 50-unit batch is tested one at a time. Each test requires 9 minutes. The completed batch, after all testing, is sent to shipping for packaging and final shipment to customers. A complete batch of 50 units is sent from testing to shipping. The Shipping Department is located next to testing. Thus there is no mave time between these two operations. Packaging and labeling requires 7 minutes per unit. 1. Determine the amount of value-added and non-value-added lead time and the value-added ratio in this process for an average stereo unit in a batch of S0 units. Categorize the non-value-added time into wait and move time. Round the percentage to one decimal place Value-added lead time Non-value-added lead time: Wait time lead time Move time lead time Total non-value-added lead time Total lead time Value-added ratio (as a percent) Move time in this process could best be reduced by a. Doing nothing b. Changing the layout from a process orientation to a product orientation. .Increasing batch sizes. d. Eiminating the testing step e. Hiring more workersExplanation / Answer
1) Board Assembly time 4 Value Added Final Assembly time 22 Value Added Move time from Final to testing 0.4 Moving time Movinig time from Board to Final Assembly 0.2 Moving time Test Set up Time 30 Waiting time Testing time 9 Value Added Packagiing & Labelliing Time 7 Value Added Total Time 72.6 Value added time 42 Non Vale added time 30.6 - wait time 30 - Move time 0.6 Value added ratio(%) 57.85% 2 Move time can be reduced by increasing batch size
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.