Preble Company manufactures one product. Its variable manufacturing overhead is
ID: 2430845 • Letter: P
Question
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:
The planning budget for March was based on producing and selling 29,000 units. However, during March the company actually produced and sold 34,000 units and incurred the following costs:
Purchased 160,000 pounds of raw materials at a cost of $8.50 per pound. All of this material was used in production.
Direct laborers worked 59,000 hours at a rate of $14 per hour.
Total variable manufacturing overhead for the month was $564,040.
6. If Preble had purchased 174,000 pounds of materials at $8.50 per pound and used 160,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values. Do not round intermediate calculations.)
7. What direct labor cost would be included in the company’s planning budget for March?
8. What direct labor cost would be included in the company’s flexible budget for March?
9. What is the labor rate variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values. Do not round intermediate calculations.)
10. What is the labor efficiency variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values. Do not round intermediate calculations.)
Direct materials: 4 pounds at $10 per pound $ 40 Direct labor: 2 hours at $13 per hour 26 Variable overhead: 2 hours at $9 per hour 18 Total standard cost per unit $ 84Explanation / Answer
6) Material quantity variance = (34000*4-160000)*10 = 240000 U
7) Direct labour in planning budget = 29000*26 = 754000
8) Direct labour in flexible budget = 34000*26 = 884000
9) Direct labour rate variance = (13-14)*59000 = 59000 U
10) Direct labour efficiency variance = (34000*2-59000)*13 = 117000 F
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.