Based on the results of the pilot project, Patrick planned on a three-phase impl
ID: 2429980 • Letter: B
Question
Based on the results of the pilot project, Patrick planned on a three-phase implementation schedule. The start-up phase would involve one train per week carrying 200 FEU containers. Phase 2 would double the volume with two shipments per week. When the project was running at full volume in the third phase, Patrick expected Cache Creek to operate six days per week, with one shipment of 200 FEU containers to the port each day. The new trans-load operation would require 5 acres of land at Cache Creek.
Canaan would need to commit resources to support container-handling operations, scheduling, and administration. A yard manager and administrative staff for the trans-loading operation at Cache Creek needed to be hired. Canaan would also need to purchase office equipment and put in a computer system. The yard would require container-handling equipment, which could be leased, and a new pad for container storage would need to be installed. The material handling equipment would include two container stackers, each with capacity of 20 moves per hour for both unloading empty containers and loading full containers. Patrick estimated that fixed overhead costs for administrative costs, including salaries, administrative expenses, and lease payments would be $75,000 per month. The number of material handling operators in the yard would be driven by container volume, and labour costs would be recovered through fees charged to the shipper (e.g., the $400 container stuffing fee; see Exhibit 5). Initial capital costs were expected to be $200,000.
EXHIBIT 5: FINANCIAL ANALYSIS OF VARIABLE COSTS
2016,
Current
Cache Creek Model
1. Empty container shipped from Eastern Canada and repositioned at Vancouver rail yard
$ 500
$ 500
2. Truck lumber to trans-load yard
1,050
250
3a. Truck empty container from rail yard to trans-load yard
140
–
3b. Internal rail movements
–
75
4. Container stuffed at trans-load yard
400
400
5. Container delivered to dock
140
400
6. Dock charges and reservation fees
100
100
7. Dock demurrage and 3PL storage fees (average)
50
–
Total
$ 2,380
$ 1,725
Note: 3PL = third-party logistics supplier Source: Company files.
a. the container volume per week is: __200_________
b. If there are 50 weeks in a year, container volume per year is:______
2. Monthly fixed/overhead cost is:______
a. Annual (12 months) fixed or overhead cost is (exclude capital cost): _____
3. Lease cost
per month and per acre lease cost is:_______
Number of acres for lease :_______
Current
Cache Creek Model
1. Empty container shipped from Eastern Canada and repositioned at Vancouver rail yard
$ 500
$ 500
2. Truck lumber to trans-load yard
1,050
250
3a. Truck empty container from rail yard to trans-load yard
140
–
3b. Internal rail movements
–
75
4. Container stuffed at trans-load yard
400
400
5. Container delivered to dock
140
400
6. Dock charges and reservation fees
100
100
7. Dock demurrage and 3PL storage fees (average)
50
–
Total
$ 2,380
$ 1,725
Explanation / Answer
a. the container volume per week is: 200 containers *6days = 1200 containers/week
b. If there are 50 weeks in a year, container volume per year is = 1200 containers * 50weeks = 60,000containers/year
c. Monthly fixed/overhead cost is: $75,000 per month
d. Annual (12 months) fixed or overhead cost is (exclude capital cost): $75,000*12= $9,00,000
e. Lease cost per month and per acre lease cost is no sufficient info
f. Number of acres for lease : 5 ACRES
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.