(30 points) Two possible routes for a power transmission line are under consider
ID: 2428737 • Letter: #
Question
(30 points) Two possible routes for a power transmission line are under consideration. Relevant data are as follows: 5. Route 1 15 miles $5,000/mile $200/mile Route 2 5 miles $25,000/mile $300/mile 15 $5,000/mile Length of the Route Initial Cost Annual Maintenance Useful Life Scrap Value of the line at the end of $3,000/mile ars 15 years Annual Cost of Power Loss $500/mile $500/mile Assuming that all cash flows are end of period, calculate the equivalent annual costs to determine which route should be taken using a nominal annual interest rate of 8% (State your assumptions)?Explanation / Answer
5.
For Route1:
Initial cost = 5000*15 = $75000
Annual maintenance cost = 200*15 = $3000
Scrap value = 3000*15 = $45000
Annual cost of power loss = 500*15 = $7500
Time = 15 years
R = 8%
Present value of the total cost = 75000 + (3000+7500)*(1-1/1.08^15)/.08 - 45000/1.08^15
Present value of the total cost = $150688.65
Let, uniform annual cost = EUAC1
Then,
EUAC1 = 150688.65/((1-1/1.08^15)/.08)
EUAC1 = $17604.89
For Route 2:
Initial cost = 25000*5 = $125000
Annual maintenance cost = 300*5 = $1500
Scrap value = 5000*5 = $25000
Annual cost of power loss = 500*5 = $2500
Time = 15 years
R = 8%
Present value of the total cost = 125000 + (1500+2500)*(1-1/1.08^15)/.08 - 25000/1.08^15
Present value of the total cost = $151356.87
Let, uniform annual cost = EUAC2
Then,
EUAC2 = 151356.87/((1-1/1.08^15)/.08)
EUAC2 = $17682.95
Since, the uniform annual cost of route 1 is lesser than the uniform annual cost of route 2, then route 1 should be selected, because of its more cost effective nature.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.