The budget for May called for production of 9,000 units. Actual output for the m
ID: 2428390 • Letter: T
Question
The budget for May called for production of 9,000 units. Actual output for the month was 8,500 units with total direct materials cost of $127,500 and total direct labor cost of $77,775. The direct labor standards call for 45 minutes of direct labor per unit at a cost of $12 per direct labor-hour. The direct materials standards call for one pound of direct materials per unit at a cost of $15 per pound. The actual direct labor-hours were 6,375. Variance analysis of the performance for the month of May would indicate:Explanation / Answer
Budget
Actual
Per Unit
Total
Per Unit
Total
9000 Units
8500 Units
15
135000
15
127500
12
81000
12.2
77775
Material Price Variance = Actual Quantity * (Standard Price - Actual Price) = 8500 * ( 15 - 15) = 0 (No variance) Direct Labour Rate Variance = Actual Hours Worket * (Standard Rate - Actual Rate) = 6375 * (12 - 12.2) = 6375 *(-0.20) = (1275) UnfavorableRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.