Please show calculations Indiana Co. began a construction project in 2011 that w
ID: 2428219 • Letter: P
Question
Please show calculationsIndiana Co. began a construction project in 2011 that will provide it $150 million when it is completed in
2013. During 2011, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to
complete the project. Suppose that, in 2012, Indiana incurred costs of $63.75 million and estimated an
additional $42.75 million in costs to complete the project. Using the percentage-of-completion method,
Indiana:
A. Recognized a $3.75 million loss on the project in 2012.
B. Recognized a $5.25 million gross profit on the project in 2012.
C. Recognized a $7.5 million gross profit on the project in 2012.
D. None of the above is correct.
Explanation / Answer
2011 2012
Contract price $150 $150
Actual costs
todate $36 $99.75
Estimated costs
to complete $84 $42.75
Total costs $120 $142.50
Gross Profit $30 $7.50
Gross profit recognition = Actual costs x Gross profit / Total costs
For 2011 $36 x $30 / $120 = $9
Till 2012 $99.75 x $7.50 / $142.50 = $5.25
For 2012 Loss $5.25 - $9.00 = -$3.75
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.