Exercise 23-15 Burte Corporation prepared the following variance report. Fill in
ID: 2427939 • Letter: E
Question
Exercise 23-15
Burte Corporation prepared the following variance report.
Fill in the missing amounts or letters in the report. (Round price to 2 decimal places, e.g. 2.75.)
BURTE CORPORATION
Variance Report—Purchasing Department
For Week Ended January 9, 2014
Type of
Materials
Quantity
Purchased
Actual
Price
Standard
Price
Price
Variance
Explanation
BURTE CORPORATION
Variance Report—Purchasing Department
For Week Ended January 9, 2014
Type of
Materials
Quantity
Purchased
Actual
Price
Standard
Price
Price
Variance
Explanation
Explanation / Answer
Purchase price variance=(Actual price - Standard price) x Actual quantity
1.Rogue11
$4,114=($5.18-$5.01)*Actual Quantity
Actual quantity*0.17=$4,114
Actual quanity=$4,114/0.17=24,200
2. storm17
$658=4,700*(Atual price-$3.29)
Actual price-$3.29=-$658/4,700=$0.14
Actual price=$0.14+$3.29=$3.43
3. Beast 29
($0.42-SP)*20,300=-$812
$0.42-SP=-$812/20,300=-$0.04
SP=$0.42+$0.04=$0.46