Actual production= 11830 budgeted pro=12500 standard direct labor= 1.50 actual d
ID: 2426544 • Letter: A
Question
Actual production= 11830
budgeted pro=12500
standard direct labor= 1.50
actual dl=18836
standard variable=3$
actual variable = 47648
Explanation / Answer
Actual Production
11830
Packages
Budgeted Production
12500
Packages
Standard direct labour hours
1.5
Direct labour hour per package
Actual direct labour hours
18836
standard variable overhead rate
$3
Per package'
Actual variable overhead Costs'
$47,648
Actual hours worked ( Hours)
17745
Actual overhead rate ( Actual Overhead costs/Actual Production
$4
Standard Hours ( Budgeted Production * Standard direct labour hours)
18750
Variabe overhead spending variance (Actual hours worked x (Actual overhead rate - standard overhead rate))
$ 18,237
Favorable
Variable overhead efficiency variance (Standard overhead rate x (Actual hours - standard hours))
$ (3,015)
Adverse
Actual Production
11830
Packages
Budgeted Production
12500
Packages
Standard direct labour hours
1.5
Direct labour hour per package
Actual direct labour hours
18836
standard variable overhead rate
$3
Per package'
Actual variable overhead Costs'
$47,648
Actual hours worked ( Hours)
17745
Actual overhead rate ( Actual Overhead costs/Actual Production
$4
Standard Hours ( Budgeted Production * Standard direct labour hours)
18750
Variabe overhead spending variance (Actual hours worked x (Actual overhead rate - standard overhead rate))
$ 18,237
Favorable
Variable overhead efficiency variance (Standard overhead rate x (Actual hours - standard hours))
$ (3,015)
Adverse
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.