Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Brady Construction Company contracted to build an apartment complex for a price

ID: 2426005 • Letter: B

Question

Brady Construction Company contracted to build an apartment complex for a price of $4800000. Construction began in 2013 and was completed in 2015. Below are two different, independent scenarios for the project. For each scenario calculate the gross profit to be recognized in 2013, 2014 and 2105 using the percentage of completion method. Calculate the gross profit to be recognized in 2013, 2014 and 2015 using the completed contract method. Costs Incurred During Year Estimated Costs to Complete (as of year-end) to Complete (es 2014 2015 2013 1800000 1080000 2880000 1692000 1332000 2304000 2014 2015 1080000 9720000 Scenario 2013 720000 2 576000

Explanation / Answer

Situation 1

Particulars

2013

2014

2015

Contract Price

         4,800,000

         4,800,000

         4,800,000

Actuals costs to date

             720,000

         2,520,000

         3,600,000

Estimated costs to complete

         2,880,000

         1,080,000

                        -  

Total estimated Costs

         3,600,000

         3,600,000

         3,600,000

Estimated Gross profit

         1,200,000

         1,200,000

         1,200,000

Gross profit recognized under % completion method:

% Completion :

2013:$720,000/3,600,000 =20%

2014: $2,520,000/3,600,000 =70%,

2015: $3600,000/3,600,000 =100%

Gross Profit:

2013

$1,200,000 x 20%=$240,000

2014

$1,200,000 x 70%=$840,000( two years profit)

Current year Profit: $840,000-$240,000=$600,000

2015

Current year profit= Total profit – Previous year’s profit

$1,200,000-$840,000=$360,000  

Situation 2

Particulars

2013

2014

2015

Contract Price

         4,800,000

         4,800,000

         4,800,000

Actuals costs to date

             576,000

         2,268,000

       3,600,000

Estimated costs to complete

         2,304,000

             972,000

                        -  

Total estimated Costs

         2,880,000

         3,240,000

         3,600,000

Estimated Gross profit

         1,920,000

         1,560,000

         1,200,000

Gross profit recognized under % completion method:

% Completion :

2013:$576,000/2,880,000 =20%

2014: $2,268,000/3,240,000 =70%,

2015: $3600,000/3,600,000 =100%

Gross Profit:

2013

$1,200,000 x 20%=$240,000

2014

$1,200,000 x 70%=$840,000( two years profit)

Current year Profit: $840,000-$240,000=$600,000

2015

Current year profit= Total profit – Previous year’s profit

$1,200,000-$840,000=$360,000

Situation 1

Particulars

2013

2014

2015

Contract Price

         4,800,000

         4,800,000

         4,800,000

Actuals costs to date

             720,000

         2,520,000

         3,600,000

Estimated costs to complete

         2,880,000

         1,080,000

                        -  

Total estimated Costs

         3,600,000

         3,600,000

         3,600,000

Estimated Gross profit

         1,200,000

         1,200,000

         1,200,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote