Ayala Corporation accumulates the following data relative to jobs started and fi
ID: 2425392 • Letter: A
Question
Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017.
Cost and Production Data
actual
standard
2.10
10000
42500
3.00
1.30
overhead is applied on the basis of standard machine hours. Three hours of machine time are required for each direct labor hour. The jobs were sold for 400,000. Selling and administraive expenses were 40,000. Assume that the total amount of raw materials purchased equaled the amount used. a) compute all of the variances for (1) direct materials and (2) direct labor b) compute the total ovehead variance c)prepare an income statement for management.
Cost and Production Data
actual
standard
raw material unit cost 2.252.10
raw material unit used 1060010000
direct labor payroll 120960 120000 direct labor hours worked 14400 15000 manufacturing overhead incurred 14400 15000 manufacturing overhead applied 189500 machine hours expected to be used at normal capacity 193500 budgeted fixed overhead for june42500
variable overhead rate per machine hr3.00
fixed overhead rate per machine hr1.30
Explanation / Answer
A) Variances of direct materials
Given actual raw material units used (AQ) 10600 units Standard units (SP): 10000 units
cost per unit actual (AP) 2.25 Standard (SQ): 2.10
Material Cost Variance = standard cost - actual cost = (SP* SQ) - (AP*AQ) = (10000* 2.10) - (10600*2.25)
= 21000 - 23850 = 2850 A
Material price variance = standard cost of Actual Quantity - Actual Cost = (SP * AQ) - (AP * AQ) = (2.10 * 10600) - (2.25* 10600) = 22260 - 23850 = 1590 A
Material Usage Varince = standard cost of standard quantity - standard cost of actual quantity = (SQ * SP) - (AQ* SP) = (10000 * 2.10) - (10600 * 2.10) = 21000 - 22260 = 1260 A
Variances of direct labour :
Given standard cost of labour = 120000 Actual Labour cost = 120960
Standard labour hours = 14400 Actual labour hours = 15000
Standard rate per hour= 120000 / 14400 = 8.33 Actual rate per hour = 120960 / 15000 = 8.064
Labour Cost Variance = (Standard Cost – Actual Cost) = 120000 - 120960 = 960A
Labour Rate Variance = (Standard Cost of Actual Time - Actual Cost) = (SR * AH ) - (AR * AH) = (8.33 * 15000) - (8.064 * 15000) = 124950 - 120960 = 3990 F
Labour Efficiency Variance = (Standard Cost of Standard Time for Actual Production – Standard Cost of Actual Time) = ( SR * SH) - (SR * AH) = ( 8.33 * 14400) - (8.33 * 15000) = 119952 - 124950 = 4998 A
Total overhead variance = Overhead absorbed - actual overhead = (AR * SR) - (AR * AH) =
Calculation of unit factory cost
Direct material 2.10
Direct labour 8.33
Manufacturing overhead 4.30 (3.00 + 1.30)
Factory cost 14.73
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.