Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

On March 1, 2014, Pechstein Construction Company contracted to construct a facto

ID: 2424782 • Letter: O

Question

On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,091,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below. 2014 2015 2016

Contract costs incurred during the year $2,773,930 $2,882,630 $1,987,440

Estimated costs to complete the contract at 12/31 3,677,070 1,987,440 –0–

Billings to Fabrik during the year 3,486,000 3,484,000 1,121,000

(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2014 Entry field with correct answer $Entry field with correct answer 2773930 Entry field with correct answer Entry field with correct answer 3677070 Entry field with correct answer $Entry field with correct answer 6451000 Entry field with correct answer Entry field with correct answer 43 % Entry field with correct answer $Entry field with correct answer 3479130 Entry field with correct answer Entry field with correct answer 2773930 Entry field with correct answer $Entry field with correct answer 705200 2015 Entry field with correct answer $Entry field with correct answer 5656560 Entry field with correct answer Entry field with correct answer 1987440 Entry field with correct answer $Entry field with correct answer 7644000 Entry field with correct answer Entry field with correct answer 74 % Entry field with correct answer $Entry field with incorrect answer now contains modified data Entry field with correct answer Entry field with incorrect answer Entry field with correct answer $Entry field with incorrect answer 447000 2016 Entry field with correct answer $Entry field with incorrect answer Entry field with correct answer Entry field with incorrect answer Entry field with correct answer Entry field with incorrect answer Entry field with correct answer Entry field with correct answer Entry field with incorrect answer Entry field with correct answer $Entry field with incorrect answer

(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. 2014 $Entry field with correct answer 2015 $Entry field with correct answer 2016 $Entry field with incorrect answer

Explanation / Answer

(a)

Computation of Recognizable Profit/Loss

Percentage-of-Completion Method

2014

2015

2016

(b)

Computation of Recognizable Profit/Loss

Completed-Contract Method

2014 - None

2015- None

2016

Costs to date (12/31/14) $2,773,930 Estimated costs to complete 3,677,070 Estimated total costs $6,451,000 Percent complete (2,773,930/6,451,000) 43% Revenue recognized($8,091,000*43%) $3,479,130 Costs incurred $2,773,930 Profit recognized in 2014 $705,200
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote