Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

(a) Problem 133 (Part Level Submission) Warning Don\'t show me this message agai

ID: 2424297 • Letter: #

Question

(a)

Problem 133 (Part Level Submission)

Warning

Don't show me this message again for the assignment

Ok

Cancel

(a)

(a)

Problem 133 (Part Level Submission)

The board of directors of Ogle Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information:
1. Ogle commenced doing business on January 1, 2015. 2. Construction activities for the year ended December 31, 2015, were as follows: Project Total Contract
Price Billings Through
12/31/15 Cash Collections
Through 12/31/15 Contract Costs
Incurred Through
12/31/15 Estimated
Additional Costs to
Complete Contracts A $  497,000 $  337,000 $  307,000 $  421,000 $  98,000 B 717,000 207,000 207,000 190,500 444,500 C 473,500 472,000 387,000 347,000 -0- D 198,500 97,000 63,500 120,000 94,000 E 447,000 397,000 397,000 317,000 79,250 $2,333,000 $1,510,000 $1,361,500 $1,395,500 $715,750 3. Each contract is with a different customer. 4. Any work remaining to be done on the contracts is expected to be completed in 2016.

Warning

Don't show me this message again for the assignment

Ok

  

Cancel

  

(a)

Compute the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2015, which would be reported under:
(1) The completed-contract method. $ (2) The percentage-of-completion method (based on estimated costs). $ Compute the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2015, which would be reported under: (1) The completed-contract method. $ (2) The percentage-of-completion method (based on estimated costs). $

Explanation / Answer

(1) Completed contract method

Percentage completion Method

Percentage Completed = Cost incurred/Total Estimated cost

Revenue to be recognised = Total contract price x Percentage completion - cost incurred

Project Billings Cost incurred Profit/(loss) A 337000 421000 (84000) B 207000 190500 16500 C 472000 347000 125000 D 97000 120000 (23000) E 397000 317000 80000