Standard Custom A.) Compute the overhead rate using the traditional (plantwide)
ID: 2420565 • Letter: S
Question
Standard
Custom
A.) Compute the overhead rate using the traditional (plantwide) approach.
B.) Compute the overhead rates using the activity-based costing approach.
C.) Determine the difference in allocation between the two approaches.
PLEASE ANSWER ALL QUESTIONS!!
Wilkins Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.Standard
Custom
Direct labor costs $42,100 $117,000 Machine hours 1,160 1,330 Setup hours 110 380Total estimated overhead costs are $299,800. Overhead cost allocated to the machining activity cost pool is $199,900, and $99,900 is allocated to the machine setup activity cost pool.
Explanation / Answer
Standard Custom Total Overhead allocation Overhead rate A B C D D/C Direct labor costs $ 42,100 $ 117,000 $ 159,100 $ 299,800 $ 1.88435 Traditional Machine hours 1160 1330 2490 $ 199,900 $ 80.2811 Activity Based Setup hours 110 380 490 $ 99,900 $ 203.8776 Activity Based Traditional approach Standard Custom Total A B 42100*1.88435 117000*1.88435 Direct labor costs 79331 220469 299800 Activity Based Costing 1160*80.2811 1330*80.2811 Machine hours 93126.076 106773.863 199900 110*203.8776 380*203.8776 Setup hours 22426.536 77473.488 99900 Total 115553 184247 299800 Difference 36221 -36222
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.