On April 1, Sangvikar Company had the following balances in its inventory accounts:

Work-in-process inventory is made up of three jobs with the following costs:

During April, Sangvikar experienced the transactions listed below.

Materials purchased on account, $29,000.

Materials requisitioned: Job 114, $16,500; Job 115, $12,200; and Job 116, $5,000.

Job tickets were collected and summarized: Job 114, 150 hours at $12 per hour; Job 115, 220 hours at $14 per hour; and Job 116, 80 hours at $18 per hour.

Overhead is applied on the basis of direct labor cost.

Actual overhead was $4,415.

Job 115 was completed and transferred to the finished goods warehouse.

Job 115 was shipped, and the customer was billed for 125 percent of the cost.

Required:

1. Calculate the predetermined overhead rate based on direct labor cost.

% of direct labor cost

2. Calculate the ending balance for each job as of April 30.

3. Calculate the ending balance of Work in Process as of April 30.

$

4. Calculate the cost of goods sold for April.

$

5. Assuming that Sangvikar prices its jobs at cost plus 25 percent, calculate the price of the one job that was sold during April.

Ending Balance Job 114 $ Job 115 $ Job 116 $ Materials Inventory Work-in-Process Inventory Finished Goods Inventory $12,730 21,340 8,700

Explanation / Answer

Solution-1

Predetermined overhead rate =  Applied Overhead / Direct Labor

Predetermined overhead rate = $1,170/ 1,800

Predetermined overhead rate =65% direct labor cost

Solution-2

Solution-3

Ending Work in Process (Jobs 114 and 116)

Solution-4

Job 115 = $22,496

So, Cost of Goods Sold (April) = $22,496

Solution-5

Price (Job 115) = $22,496*125%

Price (Job 115) = $28,120

Job 114 Job 115 Job 116 Balance, April 1 $5,381 $5,214 $10,745 Direct Material 16,500 12,200 5,000 Direct Labor 1,800 3,080 1,440 Applied Oerhead 1,170 2,002 936 Total $24,851 $22,496 $18,121