Elaydo Inc. makes flavored water and performs the following tasks in the beverag
ID: 2418414 • Letter: E
Question
Elaydo Inc. makes flavored water and performs the following tasks in the beverage manufacturing process:
Hours
Receive and transfer ingredients to storage 9.4
Store ingredients 261.1
Transfer ingredients from storage to production area 3.5
Mix and cook ingredients 6.8
Bottle water 2.5
Transfer bottles to finished goods warehouse 4.9
a. Calculate the total cycle time of this manufacturing process. Round your answer to one decimal place.
Elaydo Inc. makes flavored water and performs the following tasks in the beverage manufacturing process:
a. Calculate the total cycle time of this manufacturing process. Round your answer to one decimal place.
hours
b. Calculate the manufacturing cycle efficiency of this process. Round your percentage answer to one decimal place, if rounding is required. For example, 5.78% would be entered as "5.8" in the answer box below.
%
Elaydo Inc. makes flavored water and performs the following tasks in the beverage manufacturing process:
a. Calculate the total cycle time of this manufacturing process. Round your answer to one decimal place.
_____hours
b. Calculate the manufacturing cycle efficiency of this process. Round your percentage answer to one decimal place, if rounding is required. For example, 5.78% would be entered as "5.8" in the answer box below.
______%
Explanation / Answer
Activity
Hours
Receive and transfer ingredients to storage
9.4
Non value added time
Store ingredients
261.1
Non value added time
Transfer ingredients from storage to production area
3.5
Non value added time
Mix and cook ingredients
6.8
Value added time
Bottle water
2.5
Value added time
Transfer bottles to finished goods warehouse
4.9
Non value added time
Total Time take for manufacturing process (A)
288.2
SUM(E4:E9)
Total value added time (B)
9.3
Total non value added time (C )
278.9
MCE (B/A)
0.03
Activity
Hours
Receive and transfer ingredients to storage
9.4
Non value added time
Store ingredients
261.1
Non value added time
Transfer ingredients from storage to production area
3.5
Non value added time
Mix and cook ingredients
6.8
Value added time
Bottle water
2.5
Value added time
Transfer bottles to finished goods warehouse
4.9
Non value added time
Total Time take for manufacturing process (A)
288.2
SUM(E4:E9)
Total value added time (B)
9.3
Total non value added time (C )
278.9
MCE (B/A)
0.03