Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The Shawshank Manufacturing Co. uses a job order cost system of accounting. The

ID: 2416142 • Letter: T

Question

The Shawshank Manufacturing Co. uses a job order cost system of accounting.  The following information was taken from the books of the company after all posting had been completed at the end of January: (35 points)

Jobs
Completed

Direct
Materials Cost

Direct
Labor Cost

Factory
Overhead

Units
Completed

101     

$1,800    

$2,000    

$1,000    

200    

102     

1,235    

1,250    

  890

  150

104     

900    

850    

350    

100    

a.

Prepare the journal entries to allocate the costs of materials, labor, and factory overhead to each job and to transfer the costs of jobs completed to Finished Goods.

b.

Compute the total production cost of each job.

c.

Compute the unit cost of each job.

d.

Compute the selling price per unit for each job, assuming a mark-on percentage of 40 percent.

Jobs
Completed

Direct
Materials Cost

Direct
Labor Cost

Factory
Overhead

Units
Completed

101     

$1,800    

$2,000    

$1,000    

200    

102     

1,235    

1,250    

  890

  150

104     

900    

850    

350    

100    

Explanation / Answer

a) prepare journal entries to the cost of materials,labor, and factory overhead to each job and transfer the cost of jobs completed to finished goods

(1) Raw materials were used in each job.

Work in Progress ( job 101 )

$1,800

Work in Progress ( job 102 )

$1,235

Work in Progress ( job 104 )

$900

Inventories

$3,935

(2) Total direct labour cost incurred for each job.

Work in Progress ( job 101 )

$2,000

Work in Progress ( job 102 )

$1,250

Work in Progress ( job 104 )

$850

Labour expenses

$4,100

(3) Manufacturing overheads are charged to each job

Work in Progress ( job 101 )

$1,000

Work in Progress ( job 102 )

$890

Work in Progress ( job 104 )

$350

Manufacturing overheads

$2,240


(4) The cost of each jobs are transferred from work in progress to finished goods.

Finished goods

$10,275

Work in Progress ( job 101 )

$4,800

Work in Progress ( job 102 )

$3,375

Work in Progress ( job 104 )

$2,100

b) The total production cost for each job (See in table above )

Job 101

Job 102

Job 104

4,800

3,375

2,100

c) The unit cost of each job (See in table above )

Job 101

Job 102

Job 104

24

22.50

21.00

d) The selling price per unit for each job, assuming the mark on percentage is 40% (See in table above )

Job 101

Job 102

Job 104

33.60

31.50

29.40

Table showing total production cost.cost per unit and selling price per unit for each job.

                                                                                  (In $)

Particulars

Job 101

Job 102

Job 104

Direct materials

1,800

1,235

900

Diirect labor

2,000

1,250

850

factory overhead

1,000

890

350

Total production cost (a)

4,800

3,375

2,100

Units (b)

200

150

100

Unit cost for each job (c) = (a)/(b)

24

22.50

21.00

Mark on(d)= (c)*40%

9.60

9

8.40

Selling price per unit for each job (e)= (c)+(d)

33.60

31.50

29.40

a) prepare journal entries to the cost of materials,labor, and factory overhead to each job and transfer the cost of jobs completed to finished goods

(1) Raw materials were used in each job.

Work in Progress ( job 101 )

$1,800

Work in Progress ( job 102 )

$1,235

Work in Progress ( job 104 )

$900

Inventories

$3,935

(2) Total direct labour cost incurred for each job.

Work in Progress ( job 101 )

$2,000

Work in Progress ( job 102 )

$1,250

Work in Progress ( job 104 )

$850

Labour expenses

$4,100

(3) Manufacturing overheads are charged to each job

Work in Progress ( job 101 )

$1,000

Work in Progress ( job 102 )

$890

Work in Progress ( job 104 )

$350

Manufacturing overheads

$2,240


(4) The cost of each jobs are transferred from work in progress to finished goods.

Finished goods

$10,275

Work in Progress ( job 101 )

$4,800

Work in Progress ( job 102 )

$3,375

Work in Progress ( job 104 )

$2,100

b) The total production cost for each job (See in table above )

Job 101

Job 102

Job 104

4,800

3,375

2,100

c) The unit cost of each job (See in table above )

Job 101

Job 102

Job 104

24

22.50

21.00

d) The selling price per unit for each job, assuming the mark on percentage is 40% (See in table above )

Job 101

Job 102

Job 104

33.60

31.50

29.40

  

Work in Progress ( job 101 )

$1,800

Work in Progress ( job 102 )

$1,235

Work in Progress ( job 104 )

$900

Inventories

$3,935

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote