Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March, Madtack completed and sold Job #360. Job #361 was also completed but was not sold by the end of March. Job #359 was not completed by the end of March. Madtack's actual overhead cost for the month of March totaled $8,500. Calculate Madtack's cost of goods sold after the overhead variance is closed for March. Do not use decimals in your answer.Explanation / Answer
BEGGINING OPENING BALANCE = 4800+6300+3500=14600
+ DIRECT MATERIAL =3300+4100+6400 = 13800
+ DIRECT LABOUR = 5000+3000+4000 = 12000
+ MOH = = 8500
TOTAL MANF EXPENSES 48 900
- END BALANCE 16600
COST OF GOODS SOLD 32300
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.