a) Calculate the Predetermined Overhead Rate

b) Calculate the amount of overhead applied to Product U

Explanation / Answer

a)predetermined overhead rate= total overhead costs/cost driver

=260000/(80000+50000)=2

b)for product U it is =2*80000=160000