Rammazzotti, Inc., is looking for feedback on company performance. The company c
ID: 2411607 • Letter: R
Question
Rammazzotti, Inc., is looking for feedback on company performance. The company compares the budget for the year with the actual costs. Data have been collected below:
Rammazzotti Inc., had the following budgeted data:
Unit sales for 2014 28,000
Unit production for 2014 28,000
Budgeted fixed overhead for 2014:
Supervision $ 800
Depreciation 2,000
Rent 100
Budgeted variable costs per unit:
Direct materials $0.15
Direct labor 0.20
Supplies 0.02
Indirect labor 0.05
Power 0.02
The following actually occurred:
Actual unit sales for 2014 27,000
Actual unit production for 2014 29,000
Actual fixed overhead for 2014:
Supervision $ 850
Depreciation 2,000
Rent 150
Actual variable costs:
Direct materials $3,500
Direct labor 4,900
Supplies 530
Indirect labor 1,250
Power 470
1. Refer to Figure 8-8. The static budget variance for total fixed overhead is
a. $50 U.
b. $50 F.
c. $-0-.
d. $100 U.
2. Refer to Figure 8-8. The static budget variance for direct materials is
a. $700 F.
b. $700 U.
c. $400 F.
d. $400 U.
3. Refer to Figure 8-8. The total flexible budgeted costs for 2014 are
a. $12,560.
b. $15,660.
c. $13,510.
d. $15,220.
4. Refer to Figure 8-8. The flexible budget for direct materials cost in 2014 is
a. $3,500.
b. $4,350.
c. $4,200.
d. $4,800.
5. Refer to Figure 8-8. The flexible budget variance for indirect labor for 2014 is
a. $200 F.
b. $150 F.
c. $150 U.
d. $200 U.
6. Refer to Figure 8-8. The flexible budget variance for total cost for 2014 is
a. $2,010 F.
b. $240 F.
c. $1,620 F.
d. $850 F.
Explanation / Answer
Solution 1:
Static budget variance for total fixed overhead = Budgeted fixed overhead - Actual fixed overhead
= ($800 + $2000 + $100) - ($850 + $2,000 + $150) = $100 U
Hence option d is correct.
Solution 2:
Static budget variance for direct materials = Budgeted material cost - Actual material cost = 28000 * $0.15 - $3,500
= $700 F
Hence option a is correct.
Solution 3:
Actual unit produced for 2014 = 29000
budgeted variable cost per unit = $0.15 + $0.20 + $0.02+ $0.05 + $0.02 = $0.44
Budgeted fixed cost = $800 + $2,000 + $100 = $2,900
total flexible budgeted costs for 2014 = 29000*$0.44 + $2,900 = $15,660
Hence option b is correct.
Solution 4:
Flexible budget for direct material cost in 2014 = 29000 * $0.15 = $4,350
Hence option b is correct.
Note: I have answered first 4 parts as per chegg policy. Kindly post separate question for answer of remaining parts.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.