Berg Company incurs $320,000 overhead costs each year in its three main departme
ID: 2410181 • Letter: B
Question
Berg Company incurs $320,000 overhead costs each year in its three main departments, setup ($20,000), machining($220,000), and packing ($80,000). The setup department performs 40 setups per year, the machining department works 5,000 hours per year, and the packing department pcks 500 orders per year. Information about Berg's two products lis as follows: Number of setups Machining hours Orders packed Number of products manufactured Product A1 20 ,000 150 600 Product B1 20 4,000 350 400 Using ABC, how much overhead is assigned to Product Ai each year? $102,000 O $64,000 $242,000 O $160,000Explanation / Answer
Answer:
Setups Cost allocated to Product A1 = 20 / 40 * $20,000 = $10,000
Machining Cost allocated to Product A1 = 1,000 / 5,000 * $220,000 = $44,000
Packing Cost allocated to Product A1 = 150 / 500 * $80,000 = $24,000
Total Overhead cost assigned to Product A1 = $10,000 + $44,000 + $24,000
Total Overhead cost assigned to Product A1 = $78,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.