Santa Monica Proper Hotel project information Original project budget: $120,000.
ID: 2405129 • Letter: S
Question
Santa Monica Proper Hotel project information Original project budget: $120,000.00 Original project duration:24 months Current project budget:$160,00.00 Current project duration:36 months Answer the following questions: What is the percentage of budget overage currently? What is the percentage of schedule overage currently? lf the contractor's fee (overhead and profit mark-up) for this project is 4%, how much fee should they have received under the original budget? How much fee will they receive under the current budget? lf there are 550 rooms, each selling for an average of $600.00 per night, how much revenue does the hotel owner stand to lose with the current projected schedule delay?Explanation / Answer
Percent over budget = (Actual Expenses - Budgeted Amount) * 100
Budgeted Amount
= (160000 - 120000) * 100
120000
= 33.33%
Percentage of schedule overage = (Current Project Duration - Original Project Duration) * 100
Original Project Duration
= (36-24) * 100
24
= 50%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.