choose the correct answer: 1). The labor efficiency variance is A. The differenc
ID: 2405055 • Letter: C
Question
choose the correct answer:
1). The labor efficiency variance is
A. The difference between the number of units planned and the actual number of units produced times the actual wage rate.
B. The difference between the flexible budget hours and the actual hours times the actual wage rate.
C. The difference between the flexible budget hours and the actual hours times the budgeted wage rate
D. The difference between the number of hours planned and the actual number of hours worked times the actual wage rate.
2). Ideal standards
A. generally provide the best motivation for workers.
B. make allowances for waste, spoilage and machine breakdowns.
C. are better suited for cash budgeting than practical standards.
D. aid the planning of managers seeking continual improvement.
3). ABC Company planned to produce 3,000 cell phone covers during November. The standards for one cell phone cover specify 6 ounces of resin at $0.30 per ounce. Actual production in November was 3,100 cell phone covers. There was an unfavorable materials price variance of $380 and a favorable materials quantity variance of $120. Based on these variances one could conclude
A. more materials were purchased than were used.
B. more materials were used than were purchased.
C. the actual cost per pound for materials was less than the standard cost per pound
D. the actual usage of materials was less than the standard allowed.
4). The following variable overhead standards have been established for a particular product:
Standard variable overhead rate $1.70 per direct labor hour
Standard labor-hours per unit of output .80 hours per unit
Budgeted production 9,800 units
The following data pertain to operations concerning the product for the last month:
Actual hours worked 7,980
Actual total variable overhead cost $14,364
Actual output 9,900 units
What is the variable overhead rate variance?
A. 798 U
B. 792 U
C. 102U
D. 238 U
Explanation / Answer
The labor efficiency variance is.
C. The difference between the flexible budget hours and the actual hours times the budgeted wage rate
is correct answer.
Explanation:
Labour Efficency Variance is calculated by following formula:
(Standard Hour required for unit produced- Actual Hour used ) Standar price or Budgeted Price.
Flexible Budgeted Hour calulated by recalculation the budgeted cost on the basis of actual unit produced .
Note: As per Chegg only first question can be solved.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.