Exercise 15-6 Job Cost Sheet Date Direct Materials Direct Labor Manufacturing Ov
ID: 2404987 • Letter: E
Question
Exercise 15-6
Job Cost Sheet
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Prepare the entry to record the completion of the job. (Credit account titles are automatically indented when amount is entered. Do not indent manually.)
Date
Account Titles and Explanation
Debit
Credit
Open Show Work
Exercise 15-6
A job cost sheet of Sandoval Company is given below.Job Cost Sheet
JOB NO. 469 Quantity 2,400 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Explanation / Answer
Cost of completed job: Direct materials 4855 =715+940+1640+1560 Direct labor 1483 =416+337+730 Manufacturing overhead 1794 =503+408+883 Total cost 8132 Unit cost 3.39 (8132/2400) 1 Direct materials Materials requisition slips Direct labor Time tickets Manufacturing overhead Predetermined overhead rate 2 Predetermined manufacturing overhead rate = 1794/1483= 121% 3 Total cost of the completed job 8132 Unit cost of the completed job 3.39 4 31-Jul Finished Goods Inventory 8132 Work in Process Inventory 8132