Exercise 4-9 Air United, Inc. manufactures two products: missile range instruments and space pressure gauges. During April, 49 range instruments and 302 pressure gauges were produced, and overhead costs of $87,985 were estimated. An analysis of estimated overhead costs reveals the following activities Activities Cost Drivers Total Cost 1. Materials handling 2. Machine setups 3. Quality inspections Number of requisitions Number of setups Number of inspections $37,925 28,500 21,560 $87,985 The cost driver volume for each product was as follow:s Cost Drivers InstrumentS Gauges Total Number of requisitions Number of setups Number of inspections 415 195 250 610 1,025 280 240 475 490 Determine the overhead rate for each activity Overhead Rate Materials handling Machine setups Quality inspections Assign the manufacturing overhead costs for April to the two products using activity-based costing. (Round per unit answers to 2 decimal places, e.g. 12.25.) Instruments Gauges Total cost assigned Overhead cost per Unit

Explanation / Answer

Requirement – 1, Overhead rate for each activity.

Overhead rate

Materials Handling

$37

Machine Setup

$60

Quality Inspections

$44

Materials Handling : $37,925 / 1,025 = $37

Machine Setup : $28,500 / 475 = $60

Quality Inspections : $21,560 / 490 = $44

Requirement – 2, Total cost assigned and overhead cost per unit

Instruments

Gauges

Total cost assigned

$38,055

$49,930

Overhead cost per unit

$776.63 per unit

$165.33 per unit

Total cost assigned - Instruments

Requisition : 415 x $37 = 15,355

Setups : 195 x $60 = 11,700

Inspection: 250 x $44 = 11,000

Total cost = 15,355 + 11,700 + 11,000 = $38,055

Total cost assigned - Gauges

Requisition : 610 x $37 = 22570

Setups : 280 x $60 = 16800

Inspection: 240 x $44 = 10560

Total cost = 22570 + 16800 + 10560 = 49,930

Overhead cost per unit – Instruments

= $38,055 / 49 Instruments

= $776.63 per unit

Overhead cost per unit – Gauge

=$49,930 / 302 Gauges

= $165.33 per unit

Overhead rate

Materials Handling

$37

Machine Setup

$60

Quality Inspections

$44