Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

NEED THE SOLUTION ON EXCEL ALONG WITH THE FORMULA VIEW On January1, 2011 Jaspers

ID: 2398236 • Letter: N

Question

NEED THE SOLUTION ON EXCEL ALONG WITH THE FORMULA VIEW

On January1, 2011 Jaspersigned a contract to construct a building for Teal fora fixed price of $3,000,000. The contract was completed in 2013. Pertinent contract information is presented below: Totals $2,290,000 2011 2012 $720,000 2013 $850,000 Costs incurred during year $720,000 Estimated cost to complete Project atyearend $1,080,000 $960,000 $0 $2,040,000 Amounts billed to customer During the year $1,400,000 800,000 $800,000 $3,000,000 Determined the amount of revenue recognized in 2011. Determine the amount of gross profit (loss) recognized in 2012. Determine the balance in both the Construction in Progress And Construction Billings accounts and determine how the net Amount of these two accounts should be reported on the 2012 Balance sheet. Determine the amount of expenses recognized in 2013 Assuming Jasper does not meetthe criteria to recognize revenue Overtime, determine the revenue recognized in 2011. a. b. c. 2 points 2 points 2 points d. e. 2 points 2 points f. Determine the amount of gross profit recognized in 2013

Explanation / Answer

Fixed price of Contract

Particulars

2011

2012

2013

Total

Cost incurred during year

         7,20,000

        7,20,000

       8,50,000

       22,90,000

Estimated cost to complete the contract

       10,80,000

        9,60,000

                 -  

       20,40,000

Total (A)

       18,00,000

      16,80,000

       8,50,000

       43,30,000

Less:-

Amount billed to customer

       14,00,000

        8,00,000

       8,00,000

       30,00,000

Total (B)

       14,00,000

        8,00,000

       8,00,000

       30,00,000

Revenue/ (Loss) to be recognised (B-A)

        (4,00,000)

       (8,80,000)

         (50,000)

      (13,30,000)

% of work to be recognised as revenue (7,20,000/18,00,000)

40.00%

42.86%

100.00%

Revenue should be recognised as a % of total contract value (ie. % * 30,00,000)

       12,00,000

      12,85,714

      30,00,000

A

Amount of Revenue to be recognised in 2011

       12,00,000

B

Amount of gross profit (loss) recognised in 2012
(1285714-880000=405714)

         4,05,714

C (a)

Construction in progress (2012)- Total cost ie. Cost incurred + Cost in WIP

       16,80,000

C (b)

Construction in Billing (2012)

         8,00,000

C{C}

Net amount (2012)
Gross amount due from customers as Asset in Balance sheet

         8,80,000

D

Amount of Expense to be recognised in 2013
(Since any loss should be recognised as an expense immediately)

          (50,000)

E

Revenue to be recognised if he cannot recognize overtime in 2011

        (4,00,000)

F

Amount of Gross profit in 2013
(Total Revenue - Total Cost)

      (13,30,000)

Fixed price of Contract

Particulars

2011

2012

2013

Total

Cost incurred during year

         7,20,000

        7,20,000

       8,50,000

       22,90,000

Estimated cost to complete the contract

       10,80,000

        9,60,000

                 -  

       20,40,000

Total (A)

       18,00,000

      16,80,000

       8,50,000

       43,30,000

Less:-

Amount billed to customer

       14,00,000

        8,00,000

       8,00,000

       30,00,000

Total (B)

       14,00,000

        8,00,000

       8,00,000

       30,00,000

Revenue/ (Loss) to be recognised (B-A)

        (4,00,000)

       (8,80,000)

         (50,000)

      (13,30,000)

% of work to be recognised as revenue (7,20,000/18,00,000)

40.00%

42.86%

100.00%

Revenue should be recognised as a % of total contract value (ie. % * 30,00,000)

       12,00,000

      12,85,714

      30,00,000

A

Amount of Revenue to be recognised in 2011

       12,00,000

B

Amount of gross profit (loss) recognised in 2012
(1285714-880000=405714)

         4,05,714

C (a)

Construction in progress (2012)- Total cost ie. Cost incurred + Cost in WIP

       16,80,000

C (b)

Construction in Billing (2012)

         8,00,000

C{C}

Net amount (2012)
Gross amount due from customers as Asset in Balance sheet

         8,80,000

D

Amount of Expense to be recognised in 2013
(Since any loss should be recognised as an expense immediately)

          (50,000)

E

Revenue to be recognised if he cannot recognize overtime in 2011

        (4,00,000)

F

Amount of Gross profit in 2013
(Total Revenue - Total Cost)

      (13,30,000)