QUESTION1 4 points The following are budgeted data: Production (units) 15,000 16
ID: 2396894 • Letter: Q
Question
QUESTION1 4 points The following are budgeted data: Production (units) 15,000 16,000 Sales (units) 12,000 17,000 15,000 13, May. Each unit requires 0.75 hours of direct labor at a cost of $6.50 per hour. What is the cost of direct labor for May? O $73,125 $82,875 O $63,375 O $78,000 QUESTION2 4 points The Tobler Company had budgeted production for the year as follows: 2 Production in units 10,000 12,000 16,000 14,000 Four pounds of raw materials are required for each unit produced. Raw materials on hand at the start of the year total 4,000 lbs. The raw materials inventory at the end of each quarter should equal 1 needs in materials. Budgeted purchases of raw materials in the third quarter would be (in lbs.) O 63,200 lbs. C 62,400 lbs. 0 56,800 lbs. O50,400 lbs the next quarter's production AllExplanation / Answer
1. Production = 16000 Units
Direct Labor Hrs = 0.75
Direct Labor Cost = 6.50$ per Hour
Cost of Direct Labor for May = 16000 * 0.75 * 6.50$ = $78000 (Option D)
2. Budgeted Purchases of materials in Q3
Budgeted Purchases = 10% of Q4 Material Needs + Consumption in Q3 - 10% of Q3 Material Needs
Budgeted Purchases = 10% * 14000 * 4 Pounds + 16000 * 4 Pounds - 10% * 16000 * 4
Budgeted Purchases = 5600 Pounds + 64000 Pounds - 6400 Pounds
Budgeted Purchases = 63200 Pounds (Option A)
3. Supplies cost in Flexible Budget
Supplies Cost = $2240 Per Month + $6 Per Frame
Supplies Cost = $2240 + $6 * 810
Supplies Cost = $2240 + $4860
Supplies Cost = $7100 (Option D)
4. It is False. Because of decrease in activity doesn't result in decrease in VC per unit in flexible budget but will result in total VC decrease but not in cost per unit
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.