During 2017, Whispering Company started a construction job with a contract price
ID: 2395889 • Letter: D
Question
During 2017, Whispering Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available 2017 2018 2019 Costs incurred to date Estimated costs to complete Billings to date Collections to date $410,000 $754,800 $1,067,000 90,000 355,200 297,000 899,000 1,610,000 272,000 818,000 1,437,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized in 2018 Gross profit recognized in 2019 sExplanation / Answer
*Various accounts is used to represent Material, Accounts Payable, Cash e.t.c
Completed Contract Method:
Dear Student,
Best effort has been made to give quality and correct answer. But if you find any issues please comment your concern. I will definitely resolve your query.
2017 2018 2019 Contract price $ 1,610,000 $ 1,610,000 $ 1,610,000 Actual cost to Date $ 410,000 $ 754,800 $ 1,067,000 Estimated Cost to complete $ 590,000 $ 355,200 $ - Total Estimated Cost $ 1,000,000 $ 1,110,000 $ 1,067,000 Estimated Gross ProfitContract Price- Estimated Cost) $ 610,000 $ 500,000 $ 543,000 % Completion 41% 68% 100% Gross Profit Earned till Date $ 250,100 $ 340,000 $ 543,000 Gross Profit of Previous Year $ 250,100 $ 340,000 Gross Profit recognised $ 250,100 $ 89,900 $ 203,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.