?J&J Materials and Construction Corporation produces mulch and distributes the product by using dump trucks. The company uses budgeted fleet hours to allocate variable manufacturing overhead. The following information pertains to the? company's manufacturing overhead? data:
Budgeted output units 690 truckloads
Budgeted? machine-hours 621 hours
Budgeted variable manufacturing overhead costs for 690 loads ?$94,392
Actual output units produced 630 truckloads
Actual? machine-hours used 546 hours
Actual variable manufacturing overhead costs ?$89,592
What is the? flexible-budget amount for variable manufacturing? overhead? (Round intermediary calculations two decimal places and your final answer to the nearest whole? dollar.) A. ?$94,392 B. ?$81,801 C. ?$86,184 D. ?$89,592
Explanation / Answer
Ans is C $86,184
Explanation: Budgeted machine hour per truckload = 621/690 = 0.9 Hr
Budgeted machine hour rate = 94392/621 = $152 per machine hour
Flexible hour for 630 truckloads = 630 x 0.9 = 567 Hours
Total flexible budget for 630 truckloads = 567 hours x $152 = $86,184